CONCRETE SEAWALL REPAIRS KEYS ENERGY SERVICES, KEY WEST, FL

Client: Keys Energy Services Utility Board of the City of Key West Contract #: 24-0434 Contract Amount: $2,200,010 Work consisted of Design-Build Turnkey Construction which included a pre-construction underwater site investigation, benthic survey, FDEP & USACE Permitting. On-site work consisted of demolition of 555 lf of existing concrete bulkhead, underwater repairs of the existing bulkhead…

REBUILD ST. JOSPEH BAY ENTRANCE A RFL AND ENTRANCE C RRL

Client: U. S. Coast Guard Civil Engineering Unit – Miami Contract #: 70Z08219DPMV11600 Contract Amount: $1,686,412 Project required the demolition of the existing 54″ dia. concrete monopile and 42″ dia. steel monopile structures. Design, fabricate, and install two new range light structures meeting optical navigational height as required for the existing range system. Installation of…

MULLET KEY CHANNEL RANGE FRONT LIGHT EMERGENCY REPLACEMENT

Client: United Tugs c/o U. S. Coast Guard Civil Engineering Unit – Miami Contract #: 10902414 Contract Amount: $435,000 Project required underwater demolition of the existing range structure. In-house design, fabrication, and installation of a new range light structure meeting optical navigational height as required for the existing range system. Installation of structure included driving…

CALCASIEU EAST JETTY AID TO NAVIGATION STRUCTURE REPLACEMENT

Client: U.S. Coast Guard Civil Engineering Unit – Miami Contract #: HSCG82-17-J-PMV252 Contract Amount: $747,831 Work included In-House Design, Fabrication, and Installation of a three pipe pile navigation structure. The structure had three 175′ long driven pipe piles and one 90′ sacrificial pipe pile, all 24″ diameter. The navigational structure includes 65,000 lbs of fabricated…

PIERS 501, 502, AND 503

Client: NAVFAC Southeast Dept. of Public Works G. M. Hill Engineering Contract #: N69450-18-C-8815 Contract Amount: $580,628 Work included modification, repair, and replacement of the existing USN Dive School Piers. Pier 501 was extended an additional 36 feet increasing the structure to 268 SF. Pier 502 was completely removed and replaced. New pier was 67-feet…

WHARF REPAIRS

Client: U.S. Army Corps of Engineers Wilmington District Contract #: W912PM-17-C-0013 Contract Amount: $2,762,232 Project included 2,000 LF of epoxy injection crack repairs along eight (8) center wharf concrete beams, replacement of the South Wharf fender system, replacement of the North Wharf fender piles and wales. Install two new concrete piles and incorporated deck tie-in…

LCU RAMP REPAIRS

Client: U.S. Army Corps of Engineer Wilmington District Contract #: W912PM-17-C-0022 Contract Amount: $1,035,178 Project included installation of concrete floating docks, precast concrete pilings, steel sheet pile breakwater, rip rap stone shoreline protection, rebuilding of existing timber docks. Installation of temporary cofferdam and dewatering system, demolition of existing articulated concrete ramp, and installation of new…