Snug Harbor

Client: City of Panama City Contract #: PC22.009 Contract Amount: $4,131,857.00 Work consisted of constructing 500 linear feet of seawall with composite sheet piles and concrete cap, precast and cast-in-place concrete boat ramp, 300′ of floating dock and timber pier system, 110,000 sf of stabilizing parking lot with 4,200 tons of crushed concrete base and…

HURRICANE IAN EROSION RESTORATION

Client: Keys Energy Services Contract #: C23-0002 Contract Amount: $535,010.00 Repair 930′ of rip rap seawall and construct 700′ of concrete curb to include demolition of existing existing concrete barrier, filling and compacting FDOT road base, reclaiming rip rap boulders and reinstalling along waterside of seawall, forming and pouring new concrete curb along fence line.…

FEMA EMERGENCY BERM (DUNE) PROJECT

Client: Gulf County Board of County Commissioners Contract #: 2021-13 Contract Amount: $9,906,186.50 Indian Peninsula Segment Work consisted of constructing 20,457 linear feet of shoreline berm which incorporated a volume of 124,580 cubic yards of sand and 589,000 native dune plantings. Beacon Hill Segment Work consisted of constructing 14,520 linear feet of shoreline berm which…

SUDDUTH PARK SITE WORK IMPROVEMENTS

Client: City of Panama City Contract #: PC21-034 Contract Amount: $1,331,065 Work included selective demolition and earthwork grading, storm sewer and field drainage systems, underground utilities, cast-in-place concrete sidewalks, gravity retaining wall, curbs, and parking areas, ball-field fencing and screens, pavilion with picnic tables, park benches and trash receptacles, and ball-field clay with mound and…

WHARF REPAIRS

Client: U.S. Army Corps of Engineers Wilmington District Contract #: W912PM-17-C-0013 Contract Amount: $2,762,232 Project included 2,000 LF of epoxy injection crack repairs along eight (8) center wharf concrete beams, replacement of the South Wharf fender system, replacement of the North Wharf fender piles and wales. Install two new concrete piles and incorporated deck tie-in…

LCU RAMP REPAIRS

Client: U.S. Army Corps of Engineer Wilmington District Contract #: W912PM-17-C-0022 Contract Amount: $1,035,178 Project included installation of concrete floating docks, precast concrete pilings, steel sheet pile breakwater, rip rap stone shoreline protection, rebuilding of existing timber docks. Installation of temporary cofferdam and dewatering system, demolition of existing articulated concrete ramp, and installation of new…

DESIGN BUILD ACOUSTIC TEST FACILITY PIER

Client: U.S. Navy NAVFAC SE ACT, Inc. Contract #: N69450-13-C-6084 Contract Amount: $1,161,500 Project included demolition of existing metal building, concrete pier and pilings. Dredging for new pier construction, drive in place 12 pre-stressed concrete pilings (18″x 60′), install prestressed concrete beams, deck panels and pour in place” pier covering. Erect new pre-engineered metal building,…