Bay County District Schools (Prime Contractor) Contract No: Re-Roof Tom P. Haney Vo-Tech Membrane Roof 15/16 Contract Amount: $1,796,284 Performance Period: 180 Days (12/9/2015 – 6/8/2016) POC: Larry Taylor, Architect, (850) 785-9839 Remove 140,000 square feet of existing membrane roofing system. Replace with 140,000 square feet of 50 MIL PVC roofing system. Additional work includes […]
Tag Archives: roof replacements
Design & Build Roof Replacement Building 827, US Air Force
Inland was awarded a design and build roof replacement project for the US Air Force at Little Rock Air Force Base, Arkansas. Design/Build Roof Replacement Building 827 US Air Force Little Rock AFB, Arkansas Department of the Air Force, 19th Contracting Squadron (Prime Contractor) Contract No: FA4460-15-C-0010 Contract Amount: $822,516.36 Performance Period: 210 Days (9/23/2015 […]
Roof Replacement Buildings 729 & 744 for US Air Force
Inland was awarded a roof replacement project of the US Air Force at Dobbins Air Reserve Base, Georgia. Roof Replacement Buildings 729 & 744 US Air Force Dobbins ARB, Georgia Department of the Air Force, 94 CONF/LGC (Prime Contractor) Contract No: FA6703-15-C-0008 Contract Amount: $1,045,611.67 Performance Period: 180 Days (9/21/2015 – 3/20/2016) POC: MAJ Benjamin […]
Roof Replacement – Main Post Office Columbus, Indiana

Inland was awarded a roof replacement project for the US Postal Service in Columbus, Indiana. Work included the removal and installation of 50,000 square feet of 60 MIL PVC roofing system. Roof Replacement at Main Post Office Columbus, Indiana US Postal Service Northern Facilities Construction CMT (Prime Contractor) Contract No: 089495-15-B-0321 Contract Amount: $550,500.00 Performance […]
Roof Replacement at Main Post Office Savannah, Georgia

US Postal Service Northern Facilities Construction CMT (Prime Contractor) Contract No: 089495-14-B-0103 Contract Amount: $762,000.16 Performance Period: 250 Days (1/29/2015 – 9/19/2015) POC: Richard Russo, Contract Specialist (860) 285-7014 Removal of 65,000 square feet of existing EPDM and built-up roof systems and installation of new 60 MIL PVC roofing system with interior drain systems.
Roof Replacement at Coast Guard Sector New Orleans, Louisiana

US Coast Guard Civil Engineering Unit Miami (Prime Contractor) Contract No: HSCG82-10-D-PMVA36 / Task Order No: HSCG82-15-R-PMV043 Contract Amount: $521,900.05 Performance Period: 120 Days (1/9/2015 – 5/27/2015) POC: Carlos Garcia, Contracting Officer (305) 278-6722 Removal of 20,000 square feet of existing modified bitumen roofing system, and installation of torch/hot mopped modified roofing system with new […]
Roof Replacement Phase V, Butner NC
Inland was awarded a contract to remove and replace roofing systems on five buildings for the Federal Bureau of Prisons in Butner, NC. 50,000 total square feet of roofing systems. Roof Replacement Phase V Federal Correctional Complex Butner, North Carolina Federal Bureau of Prisons (Prime Contractor) Contract No: DJBP016N7U10001 Contract Amount: $986,216.64 Performance Period: 544 […]
Replace Roof – FCI Marianna, Florida
Federal Bureau of Prisons (Prime Contractor) Contract No: DJBP0308NPZ Contract Amount: $838,144.93 Performance Period: 470 Days (3/15/2013 – 6/30/2014) POC: Bobby Addison, Contracting Officer, (678) 686-1414 Remove mechanically fastened single ply roofing system and install fully adhered PVC roofing system approximately 50,000 Square Feet along with installation of coping metal.
Roof Replacement A. Crawford Mosley High School
Bay County District Schools Contract No: A. Crawford Mosley H.S. Roof Replacement 12/13 Contract Amount: $1,048,228.99 Performance Period: 150 Days POC: Larry Taylor, Architect, (850) 785-9839 Install Duro-Last PVC Roofing System approximately 180,000 square feet with 25,000 feet of roof coating/liquid applied membrane. Remove and replace gutters and downspouts.
Roof Replacement Phase 4 – Federal Correction Complex Butner, North Carolina
Federal Bureau of Prisons (Prime Contractor) Contract No: DJBP0106L1X10001 Contract Amount: $1,050,935.67 Performance Period: 730 Days (9/4/2012 – 9/3/2014) Completed 12/20/2013 POC: Mellissa Rhinehart, Contracting Officer, (301) 317-3255 Remove and replace 60,000 square feet of foam and modified roofing system on five active prison buildings. New roofing system includes roof drains, metal coping and accessories. […]