Design/Build West Ramp Apron & Wash Rack Airfield Pavements Phase II

USCG Support Center Elizabeth City, North Carolina Contract No: HSCG83-08-C-3WG064 Contract Amount: Design: $126,000.00 Build: $2,224,000.00 Performance Period: 60 Days (9/22/2008 – 11/22/2008) POC: Pamela Komer, USCG Civil Engineering Unit – Cleveland Design new concrete apron pavements to replace failed pavements due to soil stabilization issues. Pavements include west ramp concrete apron and wash rack. […]

Design/Build Runway & Apron Pavements Phase I

USCG Support Center Elizabeth City, North Carolina Contract No: HSCG83-07-D-3WG018 Contract Amount: Design: $136,570.71 Build: $2,896,926.00 Performance Period: 180 Days (Design & Build) (6/27/2007 – 12/30/2007) POC: Pamela Komer, USCG Civil Engineering Unit – Cleveland Design new runway pavements to replace existing failed runway due to soil stabilization issues. Pavements included runway 10/28, taxiway & […]