Wharf Repairs, Military Ocean Terminal Sunny Point, NC
U. S. Army Corps of Engineers – Wilmington District, NC
Contract No. W912PM17-C-0013
Contract Amount: $2,762,232.00
Work included 2000 lf of epoxy injection crack repairs along eight center wharf concrete beams, replacement of the South wharf fender system, replacement of the North wharf fender piles and wales, install two new concrete piles and incorporated deck tie-in, and the repair and restoration of the existing wave attenuator system to include filling all steel pipe piles with concrete, replacement of missing pile caps, replacement of the cathodic protection system, waterbalsting and re-coating of all sheet piles and pipe piles, and the removal of all abandoned utilities and scour system along the underside of the North wharf.